Rule Change: RC_2008_14

A Rule Change Proposal made by the Independent Market Operator on 10 June 2008
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Information from Network Operators

Market Rules Affected: 4.11.5 and 10.2.2

Date Submitted: 10 June 2008

Date First Published on the IMO Website: 13 June 2008

Date Final Report Published: 20 October 2008

Current Status: Closed for public submissions. Procedure Change Report being prepared. Publication date TBA

Event Date Comments
Proposal Received by IMO 10/06/2008  
Notification Published 13/06/2008  
First Submission period 13/06/2008 – 25/07/2008 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 22/08/2008 Must be published within 20 B-Days after the end of the submission period
Second submission period 25/08/2008 – 19/09/2008 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 20/10/2008 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 1/11/2008  

 