Rule Change: RC_2008_31

A Rule Change Proposal made by Synergy on 15 December 2008
Last updated:

Type: Standard Rule Change Process

Submitter: Synergy

Title: Capacity credits for solar facilities

Market Rules Affected: Clauses 4.11.2, 4.11.3, 4.11.3A and 4.11.3B.

Date Submitted: 15 December 2008

Date First Published on the IMO Website: 18 December 2008

Current Status: Closed.

Event Date Comments
Notification Published 18/12/2008  
First Submission Period 18/12/2008 – 5/02/2009 The submission period is 6 weeks from the date the IMO published the notification
Draft Report Published 20/02/2009 Must be published within 20 B-Days after the end of the submission period
Second Submission Published 23/02/2009 –24/04/2009 This period has been extended in accordance with the notice of extension published on 12 March 2009
Final Report Published 22/05/2009 Must be published within 20 B-Days after the end of the second submission period
Commencement Not applicable The Rule Change Proposal was rejected by the IMO

 