Rule Change: RC_2009_29

A Rule Change Proposal made by the Independent Market Operator on 26 August 2009
Last updated:

Type: Fast Track Rule Change Process

Submitter: IMO

Title: Determination of Capacity Shortfalls for Curtailable Loads

Market Rules Affected: Clause 4.26.2D

Date Submitted: 26 August 2009

Date First Published on the IMO Website: 01 September 2009

Current Status: The amending rules commenced at 8:00am 1 October 2009

Event Date Comments
Proposal Received by the IMO 26/08/2009  
Notification Published 01/09/2009  
Requests to be consulted 07/09/2009 The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period 01/09/2009 - 21/09/2009 Must be completed within 15 B-Days from the date the notification is published
Final Report Published 29/09/2009 Must be published within 20 B-Days from the date the notification is published
Rule Commencement 01/10/2009  

 