Rule Change RC_2019_03

An active Rule Change Proposal made by the Economic Regulation Authority on 17 December 2020
Last updated:

Type: Standard Rule Change Process

Submitter: Economic Regulation Authority

Title: Method used for the assignment of Certified Reserve Capacity to Intermittent Generators

Market Rules Affected: 4.9.5, 4.9.11 (new), 4.10.2, 4.10.3, 4.10.3A, 4.11.1, 4.11.2, 4.11.3C, 4.11.3E, 7.7.5A, 10.5.1, the Glossary and Appendix 9.

Date Submitted: 17 December 2020

Current Status: Closed.

Event Date Comments
Notification Published 18/12/2020  
First Submission Period 18/12/2020 – 11/02/2021 The submission period is at least 30 B-Days from the publication of the Rule Change Notice.
Draft Rule Change Report Published 20/04/2021 The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 12 April 2021.
Second Submission Period 20/04/2021 – 19/05/2021 The submission period is at least 20 B-Days from the publication of the Draft Rule Change Report.
Final Rule Change Report Published 21/09/2023

The Coordinator rejected the Rule Change Proposal.

Commencement NA The Coordinator rejected the Rule Change Proposal.

 

Relevant Level Method

The Relevant Level model is indicative only and has been provided in good faith by the former Rule Change Panel and The Lantau Group as a guidance tool only. Results received from this model are based on data provided by AEMO in good faith and your own inputs. You should verify these inputs, the processes of the model and information obtained through the model independently.

To access the Relevant Level Method Model, go to the webpage: Relevant Level Method Model.