Participation plans completed by bidders can be accessed by the agency鈥檚 users. Following tender closing date, the agency user can select a single or multiple successful bidder鈥檚 participation plans and submit these to WA Industry Link. To review the submitted participation plans:
- Navigate to the Participation Plan Requirements page to view the tender鈥檚 status and completed participation plans.
- Click on 鈥淰iew Details鈥 to see the list of suppliers who completed participation plans for the relevant tender.
Submit a single successful bidder鈥檚 participation plan
- To select a participation plan as successful, click on the down arrow on the right side of the record and select 鈥淪elect as Successful鈥. This will update the selected status as 鈥淵es鈥. If the selection was incorrect, click on 鈥淒eselect as Successful鈥 and the selected status will be updated as 鈥淣o鈥.
- Following selection of the successful bidder鈥檚 participation plan, click on 鈥淪ummary and Review鈥. This will show a summary of the selected bidder鈥檚 participation plan.
- Click on the down arrow to the right of the record and select 鈥淪et Contract Details.鈥
- A pop-up window will appear titled Please Review Contract Details. Review and update the following details, as required:
- Contract commencement date
- Contract completion date
- Contract reference
- Contract value
- On completion click 鈥淪ave鈥.
- The updated information will be displayed in the summary of successful participation plans. To update the values for the total contract values, click on 鈥淩ecalculate Total鈥 located in the bottom left of the page.
- To submit the successful bidder鈥檚 participation plan to WA Industry Link, click 鈥淪ubmit to JTSI鈥 in the bottom right corner.
- The page will redirect back to the dashboard. The participation plan鈥檚 status will be updated to 鈥淪uccessful participation plan Submitted 鈥 Pending JTSI Review鈥.
Select multiple successful participation plans
If there is more than one successful bidder, repeat the process outlined in step one above for all successful bidders' participation plans. Once all successful bidders have been selected, continue to follow the steps, as outlined above.